| Previous Section | Table of Contents | Next Section |
PRE-DESIGN/PROGRAM VERIFICATION
The
first step in the design process will be a design initiation meeting, to be
attended by the Building Committee and all lead designers of the Project A/E
consultant team.
Project
scope, schedule, and budget will be reviewed.
The design team is expected to meet with the Building Committee and
specific user groups on this and other occasions as necessary to verify and refine
if necessary the Program requirements.
The
first major work product will be a Master Plan for development of the
site. The Master Plan should show the
total development of the site (in accordance with this Program) for
construction in multiple phases.
The
Master Plan should be in terms of mass building areas, arrangement,
circulation, etc. The Project A/E is
expected to develop and present a minimum of three site development options as
well as conceptual floor arrangement schemes and corresponding massing studies showing
the functional relationship of spaces identified in this Program and through
subsequent discussions with using personnel.
The site location is included in the Exhibits section of this
POR.
Siting
options shall include an analysis of site circulation including vehicular and
pedestrian access, locations and recommended tie-in locations to site
utilities, and an initial analysis of building code requirements, zoning
restrictions, flood plain areas, and environmental permitting requirements.
The
Master Plan should establish preliminary architectural guidelines and a
recommendation of the appropriate architectural style to employ. Include in a “Basis of Design” document that
includes architectural guidelines, site analysis, planning principles, utility
system design narratives, tabulation of areas relative to the POR area program,
drawings, etc.
Early in
the design schedule, the Project A/E is expected to develop and present several
siting options as well as multiple conceptual floor arrangement schemes showing
the functional relationship of spaces identified in this Program and through
subsequent discussions with using personnel.
These concepts must also include interior building elevations and other
sketches of an explanatory nature. The
site location is included in the Exhibits section of this POR.
Siting
options shall include an analysis of site circulation including vehicular and
pedestrian access to the building. Also,
location and access to required utilities shall be indicated. Functional requirements and work-processes of
the User shall be considered.
For a typical building project a
minimum of three concepts meetings beyond the project initiation meeting will
be required. The first concepts meeting
at a minimum will explore possible ways to place the building on the site and
begin to explore the building mass. The
second concepts meeting at a minimum will explore arrangements of the
individual spaces, including required support spaces, and building
elevations. Each concepts meeting may
involve multiple presentations to various groups and committees.
Drawings
for the first two concept meetings can be in rough form, such as butter-paper
sketches, since revisions will probably occur.
Computer imaging and modeling is encouraged. Hardcopies of all concepts to be presented
are required. All major consultants
should be present as appropriate to the level of development, as well as any
other consultant whose work is critical to the design.
At each of these initial concepts
meetings the Project A/E shall prepare and present a minimum of three (3)
different schemes. At the end of each of
the meetings the Project A/E will have a direction from the Owner for the next
concepts meeting.
The third or final concepts review
meeting will determine the arrangements of all building spaces as well as the
exterior appearance of the building.
The final concepts review meeting will occur one (1) week after the
submission of all required materials.
The final concepts drawing submission will include a site plan, floor
plans, major building section and elevations.
Also, included in the final concepts submission will be a narrative that
describes site and utility requirements, the structural and mechanical system,
the exterior materials and a cost estimate.
The A/E will not proceed to
Preliminary Design until all requirements for Concepts have been satisfied and
approval of Concepts has been received.
Minimum Requirements for Final
Concepts Submittal
·
Site
plan showing building footprint, adjacent buildings, nearest parking, access
and site improvements.
·
Floor
plan(s) showing room layout, room names, net and gross square foot per floor
·
At
least one major building section showing floor to floor dimensions. Other sections as necessary to illustrate any
special spaces in the building.
·
At
least two exterior elevations of the building.
·
At
least two exterior perspectives of the building.
·
Narrative
describing the exterior materials, utility access points and anticipated
structural and mechanical systems for the building.
·
A
cost estimate is required for this phase.
PRELIMINARY DESIGN
Preliminary Design is very similar
to Design Development as outlined by the American Institute of Architects.
The approved concept shall be
developed into Preliminary Design documents sufficient to fully reveal all
aspects of the project. This will
include all items to meet the User's needs, and development of all facility components
to fully illustrate the proposed aesthetics, construction, systems, utilities,
services, and accessories.
Between
the final concepts approval and the submission of preliminary design most
projects will require one or more meetings to identify the full requirements
for data/telecommunications, audio visual systems, security systems, food
service requirements, etc.
Results
of these meetings must be documented in a narrative describing systems and
identifying the scope that will be in the project. Include in an updated Basis of Design
document.
All submitted documents shall be complete and coordinated
between design disciplines.
The A/E will not proceed to
Preliminary Design until all requirements for Concepts have been satisfied and
approval of Concepts has been received. Completed
preliminary design documents are a result of a completed product and are not a
function of time or duration of work.
Requirements for Preliminary Design Submittal:
·
Site
plan(s) showing all site conditions, new site development, contours, all existing
and new site utilities.
·
Landscape
plan(s) showing plant materials, irrigation zones and site accessories.
·
All
floor plans showing dimensions, door swings, room number and title, room net
square foot and programmed square foot, equipment layout, furniture layout and
rated walls. Refer to the Design
Criteria section of this manual for instructions on room numbering.
·
All
major exterior elevations with materials indicated. Samples of all major exterior materials must
be available at the Preliminary Design Review Meeting.
·
Building
sections along with typical interior and exterior wall sections
·
A
preliminary room finish schedule
·
Typical
casework elevations and sections.
·
If
the building includes laboratories, provide an enlarged plan of typical
laboratories and typical casework elevation and section
·
Foundation
plan
·
Typical
structural floor plan(s)
·
Roof
plan if structurally different from floor plans
·
Typical
structural wall section(s)
·
Mechanical
and electrical site plan(s) showing all utility connections, extensions and/or
relocations.
·
Mechanical
floor plan(s) showing single line layout of ducts with size of duct and vav
boxes indicated.
·
Enlarged
floor plan(s) of all mechanical rooms showing all equipment and maintenance
areas.
·
Plumbing
floor plan(s) showing all fixtures and piping with pipe sizes indicated.
·
Electrical
floor plan(s) showing typical light fixture layout and power layout.
·
One
line diagram of electrical system showing transformer, switchgear, breakers,
emergency generator, panelboards, etc.
·
Floor
plan(s) showing typical data/telecom and audio visual layouts.
·
Enlarged
plan(s) showing layout of all data/telecom rooms, and rooms that will have
audio visual equipment.
·
Other
drawings as required to fully illustrate the project.
·
Narrative
descriptions of products, materials and systems to illustrate the level of
quality intended.
·
Preliminary
sequence of operation for the building’s mechanical system.
·
Reports
as required in this POR
·
A
cost estimate is required for this phase.
Refer to COST CONTROL of the Administrative Procedures section for
specific requirements and format for the estimate. The Base Bid scope for the design should
include all systems necessary for a fully complete bid package. The Project A/E is to recommend Additive
Alternate items that will contribute to the building usefulness for the bid
contingency plus another 5% of the budget in the event bids are lower than
estimated.
·
A
powerpoint presentation of the project that includes the site plan, floor
plan(s), building sections, building elevations, and exterior
perspectives. The exterior perspective
in the powerpoint presentation can be a digital copy of the framed perspective.
After approval of the Preliminary
Design, the A/E shall furnish the following if required by contract:
·
Presentation
rendering(s) shall consist of an exterior view and/or interior view, drawn in
perspective, at a scale of sufficient size (24" x 30" min.) to convey
a true representation of the design of the project without distortions that
would give misleading impressions.
Landscape features together with existing structures should be indicated
in a realistic manner. The perspective,
professionally prepared, may be rendered in any color media, provided suitable
reproductions can be made from the media selected and it shall be glazed with
non glare glass and framed. The name of
the project, location, and the name of the A/E shall appear along the lower
edge of the perspective. Photographs of
models are not acceptable.
·
The
A/E will provide a detailed scale model of the project, in order to give a
better understanding of the project as to scale, proportion, mass, or location,
indicating fenestration, exterior material, color, trim, walks, drives,
parking, and major landscape features.
The model shall be mounted on a wood base and protected with a plastic
cover. Scale shall be determined by the
A/E and the Owner, however, the overall dimension should not exceed 48" x
48".
DETAILED
DESIGN
Detailed Design is very similar to
Construction Documents as outlined by the American Institute of Architects.
When
authorized by the Owner, Detailed Design documents for construction of each bid
package may proceed based upon the approved Preliminary Design, which will
include comments received by the Project A/E at the Preliminary Design Review
Meeting.
PROGRESS
MEETINGS
As soon as floor plan changes from the Preliminary Design
have been completed these floor plans need to be reviewed by the Owner. This review will also confirm and establish
the final room numbering scheme for the building.
The project time schedule
identifies interim progress meetings for examination of Detailed Design
documents by Facilities Planning and Construction staff generally at 50% and
90% stages of completion. These meetings
do not constitute approval of documents to date, but are for the purpose of
answering questions and resolving problems.
The Project A/E is required to provide the Owner a letter that indicated
the percentage level of completeness of each disciplines’ documents. This letter must be presented to the Project
Manager no later than the beginning of the review meeting. Payment for these two interim reviews is
based on the Owner’s opinion of the overall completeness of the documents.
During the 50% detailed design
meeting the Project A/E needs to present to the Owner and others at least two
interior color schemes for comments.
Updates and refinements to the mechanical systems sequence of operation
need to be presented for comment. Also,
during the review the team must review cut-sheets of all major elements of the
design and pieces of equipment with the Building Committee. Examples of these are curtain wall systems,
fixed seating, audio visual equipment, air handling units, variable air volume
boxes, plumbing fixtures and light fixtures. Verify list of items requiring
cut-sheets with Owner.
During the 90% detailed design
meeting the Project A/E needs to present to the Owner and others the revised
interior color scheme for comments.
Updates and refinements to the mechanical systems sequence of operation
need to be presented for comment. Also,
during the review the team must review revised cut-sheets of all major elements
of the design and pieces of equipment with the Building Committee.
A 100% Detailed Design review
meeting will be scheduled by the Owner to include the A/E and his consultants
and the appropriate reviewers for a detailed discussion of comments. All comments from the detailed design review
meeting shall be incorporated into the final documents prior to issuance to
bidders. No lengthy addendum to correct
the bid documents is acceptable.
100%
DETAILED DESIGN REQUIREMENTS
Drawings for all divisions of work
shall be complete and thorough in all respects, well coordinated, clear, and
neatly drawn and in accordance with the highest standards of the
profession.
Completed detailed design documents
are a result of a completed product ready to be bid by contractors and are not
a function of time or duration of work.
Detailed Design documents shall not
be submitted for review until all documents are 100% complete and a complete quality
control/coordination check has been made by the Project A/E of all documents.
Upon 100% completion and after
complete quality control check of Detailed Design documents, the Project
A/E shall furnish the Owner, as minimum requirements, the following review
sets:
·
Complete
Detailed Design drawings fully coordinated among all disciplines and ready for
bidding.
·
A
cost estimate is required for this phase.
Refer to COST CONTROL of the Administrative Procedures section for
specific requirements and format for the estimate. The Base Bid scope for the design should
include all systems necessary for a fully complete bid package that is
estimated to equal the Base Bid amount.
The Project A/E is to include Additive Alternate items that will
contribute to the building usefulness for the bid contingency amount plus
another 5% of the budget in the event bids are lower than estimated.
·
Reports
as indicated elsewhere in this manual and the POR.
| Previous Section | Table of Contents | Next Section |