The estimated project schedule for design and construction is as follows: 

 

1.

Review AE (Architect/Engineer Team) Qualifications and Develop Shortlist (4-5 firms asked to interview)

 

Mar. 9, 2006

2.

AE Interviews/Selection

 

September, 2006

3.

AE Contract Negotiation

 

October 22, 2006

4.

Congregation Approval/Initiate Design

 

November, 2006

5.

Complete Schematic Design including Site Design/Master Plan

§           Program Review and Verification

§           Site Master Plan (Building Placement, Massing, Site Circulation, Parking, Utility Connections)

§           Schematic Design – All Phases

 

February, 2007

6.

Congregation Review/Approval – Schematic Design

 

March, 2007

7.

Complete Design Development – Phase 1

 

May, 2007

8.

Congregation Review/Approval – Design Development

 

June, 2007

9.

Complete Construction Documents – Phase 1

 

August, 2007

10.

Complete Fundraising/Financing and Authorize Bidding

 

September, 2007

11.

Bidding/Negotiation/Contract Award

 

September, 2007

12.

Construction Completion – Phase 1

Fall 2008

 