The estimated project schedule
for design and construction is as follows:
|
1. |
Review AE (Architect/Engineer Team) Qualifications and
Develop Shortlist (4-5 firms asked to interview) |
|
|
2. |
AE Interviews/Selection |
September, 2006 |
|
3. |
AE Contract Negotiation |
|
|
4. |
Congregation Approval/Initiate Design |
November, 2006 |
|
5. |
Complete Schematic Design including Site Design/Master
Plan §
Program Review and Verification §
Site Master Plan (Building Placement, Massing, Site Circulation, Parking,
Utility Connections) §
Schematic Design – All Phases |
February, 2007 |
|
6. |
Congregation Review/Approval – Schematic Design |
March, 2007 |
|
7. |
Complete Design Development – Phase 1 |
May, 2007 |
|
8. |
Congregation Review/Approval – Design Development |
June, 2007 |
|
9. |
Complete Construction Documents – Phase 1 |
August, 2007 |
|
10. |
Complete Fundraising/Financing and Authorize Bidding |
September, 2007 |
|
11. |
Bidding/Negotiation/Contract Award |
September, 2007 |
|
12. |
Construction Completion – Phase 1 |
Fall 2008 |