Bethel Lutheran Church DESIGN MILESTONES



Previous Section Table of Contents Next Section

PRE-DESIGN/PROGRAM VERIFICATION


The first step in the design process will be a design initiation meeting, to be attended by the Building Committee and all lead designers of the Project A/E consultant team.


Project scope, schedule, and budget will be reviewed. The design team is expected to meet with the Building Committee and specific user groups on this and other occasions as necessary to verify and refine if necessary the Program requirements.


MASTER PLAN/INITIAL CONCEPTS


The first major work product will be a Master Plan for development of the site. The Master Plan should show the total development of the site (in accordance with this Program) for construction in multiple phases.


The Master Plan should be in terms of mass building areas, arrangement, circulation, etc. The Project A/E is expected to develop and present a minimum of three site development options as well as conceptual floor arrangement schemes and corresponding massing studies showing the functional relationship of spaces identified in this Program and through subsequent discussions with using personnel. The site location is included in the Exhibits section of this POR.


Siting options shall include an analysis of site circulation including vehicular and pedestrian access, locations and recommended tie-in locations to site utilities, and an initial analysis of building code requirements, zoning restrictions, flood plain areas, and environmental permitting requirements.


The Master Plan should establish preliminary architectural guidelines and a recommendation of the appropriate architectural style to employ. Include in a “Basis of Design” document that includes architectural guidelines, site analysis, planning principles, utility system design narratives, tabulation of areas relative to the POR area program, drawings, etc.


CONCEPTS


Early in the design schedule, the Project A/E is expected to develop and present several siting options as well as multiple conceptual floor arrangement schemes showing the functional relationship of spaces identified in this Program and through subsequent discussions with using personnel. These concepts must also include interior building elevations and other sketches of an explanatory nature. The site location is included in the Exhibits section of this POR.


Siting options shall include an analysis of site circulation including vehicular and pedestrian access to the building. Also, location and access to required utilities shall be indicated. Functional requirements and work-processes of the User shall be considered.


For a typical building project a minimum of three concepts meetings beyond the project initiation meeting will be required. The first concepts meeting at a minimum will explore possible ways to place the building on the site and begin to explore the building mass. The second concepts meeting at a minimum will explore arrangements of the individual spaces, including required support spaces, and building elevations. Each concepts meeting may involve multiple presentations to various groups and committees.


Drawings for the first two concept meetings can be in rough form, such as butter-paper sketches, since revisions will probably occur. Computer imaging and modeling is encouraged. Hardcopies of all concepts to be presented are required. All major consultants should be present as appropriate to the level of development, as well as any other consultant whose work is critical to the design.

At each of these initial concepts meetings the Project A/E shall prepare and present a minimum of three (3) different schemes. At the end of each of the meetings the Project A/E will have a direction from the Owner for the next concepts meeting.


The third or final concepts review meeting will determine the arrangements of all building spaces as well as the exterior appearance of the building. The final concepts review meeting will occur one (1) week after the submission of all required materials. The final concepts drawing submission will include a site plan, floor plans, major building section and elevations. Also, included in the final concepts submission will be a narrative that describes site and utility requirements, the structural and mechanical system, the exterior materials and a cost estimate.


The A/E will not proceed to Preliminary Design until all requirements for Concepts have been satisfied and approval of Concepts has been received.


Minimum Requirements for Final Concepts Submittal



PRELIMINARY DESIGN


Preliminary Design is very similar to Design Development as outlined by the American Institute of Architects.


The approved concept shall be developed into Preliminary Design documents sufficient to fully reveal all aspects of the project. This will include all items to meet the User's needs, and development of all facility components to fully illustrate the proposed aesthetics, construction, systems, utilities, services, and accessories.

Between the final concepts approval and the submission of preliminary design most projects will require one or more meetings to identify the full requirements for data/telecommunications, audio visual systems, security systems, food service requirements, etc.


Results of these meetings must be documented in a narrative describing systems and identifying the scope that will be in the project. Include in an updated Basis of Design document.


All submitted documents shall be complete and coordinated between design disciplines.


The A/E will not proceed to Preliminary Design until all requirements for Concepts have been satisfied and approval of Concepts has been received. Completed preliminary design documents are a result of a completed product and are not a function of time or duration of work.


Requirements for Preliminary Design Submittal:



After approval of the Preliminary Design, the A/E shall furnish the following if required by contract:




DETAILED DESIGN


Detailed Design is very similar to Construction Documents as outlined by the American Institute of Architects.


When authorized by the Owner, Detailed Design documents for construction of each bid package may proceed based upon the approved Preliminary Design, which will include comments received by the Project A/E at the Preliminary Design Review Meeting.


PROGRESS MEETINGS


As soon as floor plan changes from the Preliminary Design have been completed these floor plans need to be reviewed by the Owner. This review will also confirm and establish the final room numbering scheme for the building.


The project time schedule identifies interim progress meetings for examination of Detailed Design documents by Facilities Planning and Construction staff generally at 50% and 90% stages of completion. These meetings do not constitute approval of documents to date, but are for the purpose of answering questions and resolving problems. The Project A/E is required to provide the Owner a letter that indicated the percentage level of completeness of each disciplines’ documents. This letter must be presented to the Project Manager no later than the beginning of the review meeting. Payment for these two interim reviews is based on the Owner’s opinion of the overall completeness of the documents.


During the 50% detailed design meeting the Project A/E needs to present to the Owner and others at least two interior color schemes for comments. Updates and refinements to the mechanical systems sequence of operation need to be presented for comment. Also, during the review the team must review cut-sheets of all major elements of the design and pieces of equipment with the Building Committee. Examples of these are curtain wall systems, fixed seating, audio visual equipment, air handling units, variable air volume boxes, plumbing fixtures and light fixtures. Verify list of items requiring cut-sheets with Owner.


During the 90% detailed design meeting the Project A/E needs to present to the Owner and others the revised interior color scheme for comments. Updates and refinements to the mechanical systems sequence of operation need to be presented for comment. Also, during the review the team must review revised cut-sheets of all major elements of the design and pieces of equipment with the Building Committee.


A 100% Detailed Design review meeting will be scheduled by the Owner to include the A/E and his consultants and the appropriate reviewers for a detailed discussion of comments. All comments from the detailed design review meeting shall be incorporated into the final documents prior to issuance to bidders. No lengthy addendum to correct the bid documents is acceptable.


100% DETAILED DESIGN REQUIREMENTS


Drawings for all divisions of work shall be complete and thorough in all respects, well coordinated, clear, and neatly drawn and in accordance with the highest standards of the profession.


Completed detailed design documents are a result of a completed product ready to be bid by contractors and are not a function of time or duration of work.


Detailed Design documents shall not be submitted for review until all documents are 100% complete and a complete quality control/coordination check has been made by the Project A/E of all documents.


Upon 100% completion and after complete quality control check of Detailed Design documents, the Project A/E shall furnish the Owner, as minimum requirements, the following review sets:




Previous Section Table of Contents Next Section