Bethel Lutheran Church ESTIMATED PROJECT SCHEDULE
| Previous Section | Table of Contents | Next Section |
The estimated project schedule for design and construction is as follows:
|
1. |
Review AE (Architect/Engineer Team) Qualifications and Develop Shortlist (4-5 firms asked to interview)
|
Mar. 9, 2006 |
|
2. |
AE Interviews/Selection
|
September, 2006 |
|
3. |
AE Contract Negotiation
|
October 22, 2006 |
|
4. |
Congregation Approval/Initiate Design
|
November, 2006 |
|
5. |
Complete Schematic Design including Site Design/Master Plan
|
February, 2007 |
|
6. |
Congregation Review/Approval – Schematic Design
|
March, 2007 |
|
7. |
Complete Design Development – Phase 1
|
May, 2007 |
|
8. |
Congregation Review/Approval – Design Development
|
June, 2007 |
|
9. |
Complete Construction Documents – Phase 1
|
August, 2007 |
|
10. |
Complete Fundraising/Financing and Authorize Bidding
|
September, 2007 |
|
11. |
Bidding/Negotiation/Contract Award
|
September, 2007 |
|
12. |
Construction Completion – Phase 1 |
Fall 2008 |