Bethel Lutheran Church ESTIMATED PROJECT SCHEDULE




Previous Section Table of Contents Next Section

The estimated project schedule for design and construction is as follows:


1.

Review AE (Architect/Engineer Team) Qualifications and Develop Shortlist (4-5 firms asked to interview)


Mar. 9, 2006

2.

AE Interviews/Selection


September, 2006

3.

AE Contract Negotiation


October 22, 2006

4.

Congregation Approval/Initiate Design


November, 2006

5.

Complete Schematic Design including Site Design/Master Plan

  • Program Review and Verification

  • Site Master Plan (Building Placement, Massing, Site Circulation, Parking, Utility Connections)

  • Schematic Design – All Phases


February, 2007

6.

Congregation Review/Approval – Schematic Design


March, 2007

7.

Complete Design Development – Phase 1


May, 2007

8.

Congregation Review/Approval – Design Development


June, 2007

9.

Complete Construction Documents – Phase 1


August, 2007

10.

Complete Fundraising/Financing and Authorize Bidding


September, 2007

11.

Bidding/Negotiation/Contract Award


September, 2007

12.

Construction Completion – Phase 1

Fall 2008



Previous Section Table of Contents Next Section